  • Representation to be given in the Concern Section Office.
  • Consent letter for advance payment of shifting charges to be enclosed.
  • Ownership document at new location to be produced.
  • No objection letter from Panchayat / Municipality to be produced.
  • Arrears of electricity charges if any to be cleared.
  • There shall not be any appeals / disputes filed by the customer pending.
  • Shifting charges to be paid shall include cost of actual estimate plus twenty five percent towards supervision charges.

Disclaimer: Though all efforts are made to publish accurate information, web masters do not take any responsibility for any inadvertent error. All those concerned are advised to cross check with the official data published from concerned offices of the TSNPDCL to ensure the correctness of the information provided herein.